Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Norway: PSA Carries Out Audit of Goliat FPSO Technical Barriers
Fossil Energy

July 8, 2011 · about 15 years ago

Norway: PSA Carries Out Audit of Goliat FPSO Technical Barriers

From 24-26 May 2011, the Petroleum Safety Authority (PSA) carried out an audit of the design and application of technical barriers on Goliat FPSO. Background The audit activity was based on the PSA’s main priority relating to technical and operational barriers. The audit particularly targeted establ

1 minutes read
  • LinkedIn
  • X
  • Email

From 24-26 May 2011, the Petroleum Safety Authority (PSA) carried out an audit of the design and application of technical barriers on Goliat FPSO.

Background

The audit activity was based on the PSA’s main priority relating to technical and operational barriers. The audit particularly targeted establishment and design of certain barriers in relation to regulations, standards, internal requirements, risk-related analyses and assessments.

Objective

The objective of the audit was to assess how ENI ensures compliance with safety-critical barriers in a comprehensive and consistent manner, as well as how ENI follows up to ensure that the design solutions on Goliat FPSO fulfil the regulatory requirements and preconditions in the plan for development and operation. The audit was limited to the process safety and technical safety disciplines.

Results

Through the audit PSA highlighted certain topics within process safety and technical safety. The engineering work for the FPSO was approx. 65 per cent complete, and fabrication was scheduled to start on 1 June.

One nonconformity was identified in connection with:

Furthermore, three improvement areas were identified in connection with:

[mappress] Source: PSA, July 8, 2011;

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free